2003

Investment in a next-generation production line
Initially, the site had two fusion lines with a capacity of 0.5 tonnes per hour each. In order to increase the processing capacity and modernise the facilities, Europlasma designs a new processing line with a furnace and next-generation plasma torches. This third line (L3), designed to process 2 tonnes per hour through continuous operation, was self-financed by Europlasma (investment of €18M).